Oktober, Normalisasi Ciliwung Bisa Kendalikan Banjir di Bukit Duri

Ciliwung Normalization in Bukit Duri Has Reached 34 Percent

The Ciliwung Normalization in RW 01/12 Bukit Duri, Tebet, South Jakarta has reached 34 percent of a total length of 4.4 kilometers. In October, it is targeted already functioning for flood controlling. 

It has reached 31 percent so far. If the water debit in Ciliwung is high, puddle is hoped can be controlled

According to Teuku Iskandar, Head of Ciliwung-Cisadane Flood Control Office (BBWSCC), normalization package 1 project in Bukit Duri is targeted to be completed by the end of the upcoming October. The project stretches along approximately 4.4 kilometers from Manggarai Sluice Gate to Kampung Melayu Bridge on Jalan KH Abdullah Syafi'i.

Ciawi-Sukamahi Reservoir Targeted to Reduce Ciliwung Water Level

"It has reached 31 percent so far. If the water debit in Ciliwung is high, puddle is hoped can be controlled," he expressed, when reviewing the project, Tuesday (9/5).

Besides normalization, his party also plans to minimize water channel from five points into three points. Two points of channel will be closed down and then provided with mobile pump.

The river will also be widened from 25 meters into 40-50 meters. Hopefully water debit would increase, that was originally only about 200 cubic meters per second to 570 cubic meters per second.

"This project is divided into four packages. It will have totally 19 kilometers length, stretching from Manggarai Sluice Gate to the bridge of Jalan TB Simatupang. It will spend Rp 1.18 trillion," he closed.

Linked News
Popular News indeks
  1. Jakarta Endorses New Housing Project for Residents on Railway Embankments

    access_time28-03-2026 remove_red_eye2402 personDessy Suciati
  2. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye789 personTiyo Surya Sakti
  3. Pramono Calls for Enhanced Synergy at DPRD Post-Eid Gathering

    access_time30-03-2026 remove_red_eye697 personDessy Suciati
  4. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye636 personTiyo Surya Sakti
  5. Kampung Rambutan Terminal Sees Increase in Intercity Bus Passengers

    access_time03-04-2026 remove_red_eye504 personNurito